This facility is the first of its kind in India, being a third
party independent treatment plant. It is planned with multiphase
approach. Phase I is spread across 20,000 sq. ft. with an option
for future expansions. The facility is fully
functional with all the equipment commissioning trails been
completed in January 2009. The facility is fully
equipped with power support given by 2 MW transformer & 2.2 MW
generator backup.
Existing Processes
Following are the fully functional processes that are currently undertaken:
-
Fully automated Chromic acid anodizing
-
Semi automated Boric sulphuric acid anodizing -
Titanium etching -
Chemical conversion coating -
Vacuum blasting & glass bead cleaning
-
6 axis robot operated Shot peening -
Painting booth & ovens
|
|
Following are the fully functional testing processes:
-
PH meter -
Weighing balance -
MPI machine
|
-
Chemical lab -
Hardness testing
-
Salt Spraying
|
|
|
|
| |
|
|
|
 |
 |
 |
 |
| Chromic anodizing |
Boric sulphuric anodizing |
Titanium etching |
Alchrome |
|
|
|
|
|
 |
 |
 |
 |
| Shot Blasting |
Shot Peening |
Painting booth & ovens |
PFD booth |
|
|
|
|
|
 |
|
|
|
| Salt spraying |
|
|
|
|
|
|
 |
 |
 |
 |
| PH meter |
Weighing balance |
MPI Machine |
Chemical lab |
| |
|
|
|
 |
|
|
|
| Hardness testing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|